Project Overview
About
This Project
KFM Geotech supported a 22-storey building development in Merrylands from investigation through to construction. The engagement covered geotechnical site investigation, groundwater monitoring, hydrogeological assessment, permeability testing, a dewatering management plan, vibration monitoring, inclinometer installation and movement monitoring, and construction-phase geotechnical support.
Basement excavation and shoring wall at the Merrylands 22-storey development, NSW
Site Photography
Scope of Works
Investigation & Groundwater
01
Geotechnical Site Investigation
Borehole drilling with rock coring, in-situ testing and laboratory testing to define the ground profile beneath the building footprint.
02
Groundwater Monitoring
Installation and monitoring of groundwater standpipes to establish water levels and how they vary over time.
03
Hydrogeological Assessment
Assessment of groundwater conditions and the inflow expected into the basement excavation.
04
Permeability Testing
Field permeability testing to derive the hydraulic parameters used in the dewatering assessment.
Construction Phase
Monitoring & Support
Inclinometer casing installed for ground movement monitoring at Merrylands, NSW
Rock core from borehole BH3, Merrylands NSW, cored 6.70–15.0 m
Groundwater level monitoring results plotted against rainfall, Merrylands NSW
01
Dewatering Management Plan
Preparation of the dewatering management plan governing extraction and discharge through the excavation.
02
Vibration Monitoring
Vibration logger installation and monitoring through piling and excavation adjacent to occupied properties.
03
Inclinometer Monitoring
Inclinometer installation and movement monitoring to track deflection of the retention system as excavation progressed.
04
Construction Phase Support
On-site geotechnical support through the construction phase, including inspection and testing at ground-related hold points.
Results
Project Outcomes
Groundwater, ground movement and vibration were monitored continuously alongside the construction-phase inspections, so the behaviour of the excavation and the surrounding ground was tracked against expectation as the building progressed.
Standards & Compliance
All deliverables are produced in accordance with applicable standards

AS 1726

Geotechnical Site Investigations

AS 4678

Earth-Retaining Structures

Council

Local Council Requirements

Industry

Best Practice Guidelines

Austroads

Pavement Design Guidelines

What Else We Do
Related
Services

Environmental Site Assessment & Investigation

Full suite of environmental services for development and infrastructure clients.
Learn More →

Instrumentation & Monitoring

Instrumentation and monitoring for ground movement and infrastructure stability.
Learn More →

Geo-Structure Design

Temporary and permanent geo-structure design — from due diligence through design approval and delivery.
Learn More →
Start Your Enquiry
Need Geotechnical Advice For Your Project?

Talk to our engineering team about your project requirements. We’ll clarify the scope, advise on investigation methodology, and provide a fixed-fee proposal.